Frozen and Burst Heat Exchanger Coil in Cooling Tower
When a cold snap in January caused the heat exchanger coil in the cooling tower at Northwest Tower to freeze and burst, Total Energy Systems was called in to tackle the challenging repair. This complex project required a creative solution due to the building's location, which made using a crane nearly impossible. Proximity to bus routes, electrical lines, and a busy intersection meant traditional lifting methods were off the table.
Over the weekend, we coordinated with a massive Sikorski helicopter to lift a 6,500 lb replacement coil to the roof. With precision and teamwork, we successfully installed the new coil and restored the cooling tower to full operation.
Special thanks to @Truecoursesolutions and @VIHAviation for managing the logistics and helicopter operations, as well as @Baltimore Air Coil and Hudson Sales for supplying and delivering the replacement coil on time. This was an incredible display of collaboration and problem-solving, ensuring the building’s cooling system was back up and running efficiently.